Civil engineering
The North/South line
The North/South line is a 9.7 km metro connection between the north and south of Amsterdam, which are separated by the IJ (pronounced ’ay’), a body of open water and a former sea inlet in the southernmost part of the Zuiderzee. The line begins overground in the north at Nieuwe Leeuwarderweg (Stations Noord and Noorderpark) and plunges underground on the shore of the IJ. The 7.1 km long underground line runs under the water of the IJ to Central Station and from Stationsplein goes on to Damrak, Rokin, Vijzelstraat, Ferdinand Bolstraat (Station De Pijp) and finally to Europaplein, where it continues overground to Station Zuid WTC.
The initial plans for the metro line date back to the 1960s. They were not implemented at the time because priority was given to the construction of an eastern connection. The method used in the construction of the East line, which started in 1970 and was completed in stages in 1982, involved assembling the metro tunnel from caissons. These concrete segments were sunk from ground level after demolishing the existing buildings along the tunnel route. The damage caused by the construction of this metro to the historic centre of Amsterdam, and the Nieuwmarkt district in particular, led to mounting social opposition to the metro project, culminating in violent riots. As a result, the plans for other metro lines were abandoned in 1975.

Route North/South line
"...the engineers were specifically instructed to spare the monumental historic inner city when drawing up their plans."
The late 1980s saw a revival of interest in a new metro line and in 1996 the city council decided to construct the North/South line. Given the experience with the East line, the engineers were specifically instructed to spare the monumental historic inner city when drawing up their plans. This precondition laid down by the city council and the general public determined the civil engineering approach. To avoid damaging buildings, a route was selected that followed where possible the existing infrastructure. This consisted partly of streets (Nieuwe Leeuwarderweg, Ferdinand Bolstraat) and partly of (filled-in) waterways: the IJ (Stationsplein), the River Amstel (Damrak, Rokin) and Vijzelgracht. The possibility of building a 3.8 km tunnel at ground level was ruled out because of the high-density development and shortage of space. A solution was found in the form of a bored tunnel concept. The tunnels were to be drilled at a depth of 20 to 30 metres below NAP (Amsterdam Ordnance Datum defining the city’s normal water level), deep below the wooden foundation piles of the buildings, which went down to an average of 12 metres below NAP.
Complex building methods and techniques
"At the time there was no experience of boring tunnels through a soft subsoil of sand and clay in a historic city centre such as that of Amsterdam."
At the time there was no experience of boring tunnels through a soft subsoil of sand and clay in a historic city centre such as that of Amsterdam. This meant that the metro project was a technological challenge from the start, involving the development of new construction methods and customized techniques. There were also a number of logistically and technically extremely complicated locations, such as the rail junction of Central Station where a tunnel underpass had to be constructed with no disruption to rail traffic and leaving the listed station intact. Before the national and local governments consented to construction in 2002, several technical trials and financial feasibility studies were carried out in order to draw up a realistic project management plan. When construction started in 2003, the projected completion date was 2011; this was ultimately adjusted to mid-2018.
%2012.jpg)
Construction of caisson 1 on the Damrak site
The boring of the tunnel itself caused few difficulties; it was the setbacks surrounding the construction of the deep-level stations that were mainly to blame for the delay. At Rokin, Vijzelgracht and Ferdinand Bolstraat the roughly 200 metre-long underground station structures were installed using the deepwall method. They were built up of concrete walls milled into the subsoil to an approximate depth of 35 metres. These ‘boxes’ were then excavated to a depth of roughly 25 metres. The caisson method was only applied for the stretch of open water at Damrak: here three caissons were used to build the launch shaft from which the tunnel boring machine drove off in a southerly direction.